GEPCO ENC (Electricity New Connection Online) – How to Apply for GEPCO New Connection Online 

Welcome to gepcobill.pk, your one-stop solution for all your GEPCO electricity-related queries. Are you planning to get a new electricity connection from GEPCO? Whether you’re a business owner or a homeowner, having a reliable electricity connection is essential for your daily operations. However, the process of applying for a new connection can be confusing and time-consuming. That’s where we come in to guide you through the process.

In this blog post, we will provide you with a comprehensive guide on how to apply for a GEPCO new connection. We will cover both online and in-person application processes and provide you with all the necessary information you need to know. We will also address common issues faced during the application process and provide you with helpful tips to make the process smoother.

By the end of this blog post, you’ll have a clear understanding of how to apply for a GEPCO new connection, and you’ll be able to take the first step in getting your electricity connection up and running. So, let’s dive in!

GEPCO ENC Online Application

Outline:

Step -1 : GEPCO ENC Online Application Filling Process

  • Visit the official website of GEPCO
  • Access the Centralized Website enc.com.pk for Online Applications:
  • Read the Instructions given by GEPCO Carefully
  • Select Company as GEPCO and Select Your Subdivision:
  • Select Your Category and required Load Details:
  • Select Your Connection Type:
  • Enter Applicant’s Particulars:
  • Enter Premises Details:
  • Upload Required Attachments:
  • Read and Agree Terms and Conditions Given by Gepco:
  • Final Step: Fill the Captcha Click on Submit Button.

Step -2:  Upload the Scanned Copies of Required Document for GEPCO ENC

  • Proof of ownership such as registry, actual freehold, anonymous, or allotment letter is required.
  • All pages of the proof of ownership must be attested by an Oath Commissioner, Notary Public, or Class One Officer.
  • An affidavit from the applicant stating that no electricity connection is available at the desired location and there are no pending dues is necessary.
  • In case of multiple owners, the applicant needs to provide a Power of Attorney duly attested by an Oath Commissioner in favor of the applicant from the other owners.
  • If the applicant is a tenant, a No Objection Certificate from the property owner is needed.
  • The CNIC copy of the applicant and the attested copies of CNICs of two witnesses are mandatory for the application process.
  • Information on GEPCO office locations
  • Documents required for application
  • Procedure for submitting application in person
GEPCO-Online-Application-documents-to-upload

 Additional Information Related to GEPCO ENC

  • Common problems faced during application process
  • Tips for successful application
  • Frequently asked questions (FAQs)

Conclusion

  • Summary of key points
  • Final thoughts on the application process for GEPCO ENC.

GEPCO ENC Online – How to Apply for GEPCO New Connection Online – A Step by Step guide

Are you looking to apply for a new electricity connection in Pakistan? If so, you’re in luck! With the increasing digitization of public services, it is now possible to apply for an electricity connection online.

 In this post, we’ll guide you through the process of applying for a new electricity connection through the online method for GEPCO, one of the major electricity supply companies in Pakistan.

Step 1: Visit the official website of GEPCO

To begin the process, you’ll need to visit the official website of GEPCO, which is gepco.com.pk. On the homepage of the website, you will see a tab labeled “Online New Connection Application.” Click on this tab to proceed to the next step.

Step 2: Access the Centralized Website for Online Applications:

Clicking on the “Online New Connection Application” tab will redirect you to the website http://enc.com.pk/, which is a centralized website for applying for new connections for all electricity supply companies in Pakistan. Alternatively, you can directly access the website by typing enc.com.pk into the address bar of your browser.

However, I recommend visiting the GEPCO website first to read the complete instructions in a simple and easy-to-understand language. This will help you choose the right connection type, category, and load details, as well as understand the required documents and time required for the process.

Step 3: Read the Instructions Given by Gepco Carefully

Before you start the application process, make sure to read the instructions provided on the GEPCO website or the centralized website enc.com.pk carefully. It is crucial to choose the right category and load details, as well as understand the documents required for each category. If you skip this step and start the application process right away, you may face difficulties and need to revisit the instructions.

Step 4: Select GEPCO and Your Subdivision of Gepco :

Once you have read and understood the instructions, navigate to the “Apply” tab on the enc.com.pk website. On the homepage, you will see a notice board and tabs like Home, Track, Apply, Change, Print Form, Print DN, Pay DN, and Upload DN. Click on the “Apply” tab to begin your application process.

The first step in the application process is to select GEPCO from the “Select Distribution Company” dropdown menu. Once you select GEPCO, all of its subdivisions will appear in the “Subdivision” dropdown. Choose your concerned subdivision from the list. If you don’t know your subdivision, you can check your GEPCO bill or your neighbor’s bill to find out, as it is displayed on the bill.

Step 5: Select Your Category and Load Details:

The next step is to select your category and load details. Click on the “Select Category” dropdown menu, and you’ll see five options to choose from:

  1. Category 1: Load up to 15 kW
  2. Category 2: Load above 15 kW but not exceeding 70 kW
  3. Category 3: Load above 70 kW but not exceeding 500 kW
  4. Category 4: Load above 500 kW but not exceeding 5,000 kW
  5. Category 5: All loads 66 kV and above
gepco load categories

Choose the appropriate category based on your load requirements. Remember that selecting the wrong category can result in delays and additional costs.

Step 6: Select Your Connection Type:

The 6th step in applying for a new electricity connection online is to select the appropriate connection type from the given options. The available connection types include:

  • Domestic
  • Commercial
  • Industrial
  • AgricultureTubewell
  • Temporary
  • General Services
  • Electrification (Colonies)
  • Street Light
  • Corporate Company
gepco connection types

Step 7: Enter Applicant’s Particulars:

The 7th step is to provide your particulars as the applicant. The required information includes:

  • Applicant Status: This refers to whether you are a landlord/owner or a tenant (rental).
  • Applicant Name: This refers to your name as the applicant.
  • S/O: This refers to the name of your father/husband.
  • Citizenship: This refers to whether you are a Pakistani citizen or a foreigner.
  • NIC/CNIC: This refers to your National Identity Card (NIC) or Computerized National Identity Card (CNIC) number.
  • Present Address: This refers to your current address.
  • Mobile No1: This refers to your primary mobile number.
  • Mobile No2: This refers to your secondary mobile number.
  • Contact Person Information: In case there is a need for the company to contact someone other than the applicant, the contact person information should be provided.

Step 8: Enter Premises Detail:

The 8th step is to provide details about the premises where the electricity connection is required. The required information includes:

  • No. of meters already installed: This refers to the number of meters already installed at the premises.
  • Select Meter: The applicant must select the appropriate meter from the given options.
  • Minimum Load (In KWh): This refers to the minimum load required for the premises in KWh.
  • Premises Address: This refers to the address where the new electricity connection is required.

Step 9: Upload Required Attachments:

The 9th step is to attach the required documents with the application. The required documents include:

  • Proof of ownership such as registry, actual freehold, anonymous, or allotment letter is required.
  • All pages of the proof of ownership must be attested by an Oath Commissioner, Notary Public, or Class One Officer.
  • An affidavit from the applicant stating that no electricity connection is available at the desired location and there are no pending dues is necessary.
  • In case of multiple owners, the applicant needs to provide a Power of Attorney duly attested by an Oath Commissioner in favor of the applicant from the other owners.
  • If the applicant is a tenant, a No Objection Certificate from the property owner is needed.
  • The CNIC copy of the applicant and the attested copies of CNICs of two witnesses are mandatory for the application process.

Step 10: Read and Agree Terms and Conditions Given by Gepco:

The next step is to agree to the terms and conditions of the company. The terms and conditions include:

  • The applicant agrees to get a connection from DISCO (Department of Energy). They also agree to pay the tariff and scheduled service charges as stated by the department for the services and electricity provided to them.
  • The applicant agrees to provide an attested photocopy of their CNIC with the request form and testifies that the electricity wiring is installed by an authorized contractor of the provincial government.
  • The applicant agrees to be responsible for any damage due to malfunction of wiring.
  • The applicant testifies that they do not owe any dues to DISCO/WAPDA for connection against personally owned property or for connection against previously rented property by them.
  • The applicant testifies that there was no previous connection at the place where the new connection is requested. If it is found that there was a previous connection at the same address, the applicant will be responsible to pay any remaining dues.

Final Step: Click on Submit Button to finish Gepco ENC: 

Once the applicant has read and agreed to the terms and conditions, they can click on the “I agree and have read Abridge Conditions” checkbox and submit the application.

Conclusion – Gepco ENC Online method:

In conclusion, applying for a new electricity connection online requires the applicant to provide their particulars, premises details, and attach the required documents. It is important to read and agree to the terms and conditions before submitting the application.

Gepco Instructions and Timeline for Category 1: up to 15 Kw new connection:

Gujranwala Electric Power Company Limited offers a Category One connection for those who require up to 15 kW of power. The approval process involves the respective SD and Stunt Manager operations who will assess the feasibility of providing the connection.

The process for getting a new electricity connection from GEPCO begins with the submission of an application form and relevant documents. The office issues a receipt and seniority number, creating a seniority register based on the date of receipt. The location is inspected, and if the connection is possible, the estimated cost is calculated; otherwise, the applicant is informed of the reasons.

 After payment of the estimated expenses, the wiring test report is submitted, and the priority list is prepared. The required equipment is ordered from the store, and the connection is installed by the relevant SD and Stunt Manager Operations office. The entire process takes 30 days, and GEPCO prioritizes customer service to ensure a smooth and hassle-free experience for applicants.

Sr No.TaskNo. of Days
1.Issue receipt and seniority number to the applicant and create a seniority register1 day
2.Inspect the location and assess the feasibility of providing the connection3 days
3.Estimate the cost of installation2 days
4.Issue Demand Notice for Estimate of Connection Installation Costs2 days
5.Deposit estimated expenses in the concerned bank and submit the receipt1 day
6.Provide wiring test report and verification3 days
7.Prepare priority list and issue the service connection order1 day
8.Contact the relevant store to supply the required equipment3 days
9.Issue the required order to establish the connection5 days
10.Install the connection by the relevant SD and Stunt Manager operations office5 days

In total, the connection process takes 30 days. The customer-centric approach of GEPCO aims to make this process as smooth and hassle-free as possible for our valuable customers.

Instructions for Category 2: Upto 16-70 Kilowatt hours: 

The Gujranwala Electric Power Company Limited, under Category Two (16 to 70 kW / 400 volts), requires the approval of the Exion/Deputy Manager Operations for connection applications.

 The process takes a total of 44 days and involves the issuance of a receipt and seniority number, inspection of the applicant’s place, estimation of connection cost, approval of installation, submission of expenses to the bank, verification of wiring test report, issuance of service connection order, and installation of the connection by the concerned committee consisting of Deputy Manager Operations, Stunt Managers Operations, and M&T. The customer service is the top priority of GAPCO Administration.

StepDescriptionNumber of days required
1Issue receipt of application form and seniority number1 day
2Inspect applicant’s place and evaluate possibility of connection4 days
3Estimate cost of connection2 days
4Approve installation of connection4 days
5Deliver Demand Notice for Estimated Connection Cost and Security4 days
6Applicant submits estimated expenses to bank and provides wiring test report4 days
7Issue service connection order3 days
8Contact store to supply equipment for connection installation7 days
9Install the connection15 days
Total44 days

Instructions for Category 3: upto 71-500 Kilowatt hours 

Gujranwala Electric Power Company Limited (GAPCO) offers electricity connection services to customers falling under category three, with a required power range of 71 to 500 kW and voltage of 400 volts. The process for obtaining a new connection involves several steps and can take up to 73 days to complete.

The process for obtaining an electricity connection involves the Operations Manager providing the application form and fee receipt to the applicant within one day, followed by a site inspection within one day. If the site is feasible, the cost of installation is estimated and approval is granted within four days. After approval, the estimated cost is sent to the applicant and they submit the expenses to the bank with the receipt from the office. 

The applicant also provides a certified wiring test report within four days. Within 20 days, the concerned office issues a service connection order and the connection is installed within 37 days upon equipment availability. The entire process takes 73 days, and GAPCO strives to provide exceptional customer service throughout.

StepDescriptionNumber of Days Required
1Operations Manager provides application form and fee receipt to applicant1
2Concerned office inspects site to determine feasibility1
3Cost of installation is estimated2
4Concerned office approves installation of connection4
5Estimated installation cost is sent to applicantAfter approval
6Applicant provides certified wiring test report4
7Concerned office issues service connection order20
8Concerned office contacts store for equipment supply15
9Concerned committee installs connection upon equipment availability37
Total73
Q: What is the first step to apply for a new connection with GEPCO? 

A: The first step is to visit the official website of GEPCO, which is gepco.com.pk, and click on the “Online New Connection Application” tab.

Q: How do I access the centralized website for online applications? 

A: Clicking on the “Online New Connection Application” tab on the GEPCO website will redirect you to the website http://enc.com.pk/, which is a centralized website for applying for new connections for all electricity supply companies in Pakistan. Alternatively, you can directly access the website by typing enc.com.pk into the address bar of your browser.

Q: What should I do before starting the application process? 

A: Before starting the application process, make sure to read the instructions provided on the GEPCO website or the centralized website enc.com.pk carefully. It is crucial to choose the right category and load details, as well as understand the documents required for each category.

Q: How do I select GEPCO and my subdivision in the application process? 

A: Once you navigate to the “Apply” tab on the enc.com.pk website, select GEPCO from the “Select Distribution Company” dropdown menu, and choose your concerned subdivision from the “Subdivision” dropdown.

Q: What are the different categories of load details to choose from?

A: There are five categories to choose from:
Category 1: Load up to 15 kW
Category 2: Load above 15 kW but not exceeding 70 kW
Category 3: Load above 70 kW but not exceeding 500 kW
Category 4: Load above 500 kW but not exceeding 5,000 kW
Category 5: All loads 66 kV and above.

Q: Where can I find my subdivision information? 

A: You can check your GEPCO bill or your neighbor’s bill to find out your subdivision information, as it is displayed on the bill.

Q: What are the available connection types for a new electricity connection application online?

A: The available connection types include Domestic, Commercial, Industrial, Agriculture, Tubewell, Temporary, General Services, Electrification (Colonies), Street Light, and Corporate Company.

Q: What information is required for the applicant in the online application process?

A: The required information includes Applicant Status, Applicant Name, S/O, Citizenship, NIC/CNIC, Present Address, Mobile No1, Mobile No2, and Contact Person Information.

Q: What details about the premises are required in the online application process?

A: The required details about the premises include the number of meters already installed, the appropriate meter selection, minimum load in KWh, and the premises address.

Q: What documents are required to be uploaded with the online application?

A: The required documents include Property Document Copy, Attested CNIC Copy of Applicant, Attested CNIC Copy of Witness, Neighbour Electricity Bill Copy, and Wiring Contractor’s Test Report.

Q: What are the terms and conditions that the applicant must agree to in the online application process?

A: The terms and conditions include getting a connection from DISCO, paying the tariff and scheduled service charges, providing an attested photocopy of CNIC, being responsible for any damage due to malfunction of wiring, testifying no dues to DISCO/WAPDA, and testifying no previous connection at the same address.

Disclaimer by author: I created this post after great research and optimizing information given on official gepco website.